Questions are now emerging
over the actual contractor behind the construction of the 18-storey building
that collapsed in Eastleigh, Nairobi, eight days ago, with investigations
pointing to the possible involvement of an unqualified contractor.
Sources close to
the investigations have told Citizen TV that the project may have been
undertaken by an individual who is not registered as a contractor.
The director of
Stromax Holdings E.A. Limited, the company listed by the National Construction
Authority (NCA) as the contractor, has since distanced himself from the
construction.
In his statement
to police, the director claimed his brother, who is not a registered
contractor, asked to use the company’s details to secure NCA approvals.
He says he granted
the request and even responded to official NCA emails, confirming that his
company was undertaking the project, despite claiming he had no involvement in
the construction.
But in a twist,
the director’s brother has reportedly offered a different account, shifting
responsibility back to Stromax Holdings E.A. Limited.
He claims the
company engaged him as a labour contractor to oversee structural works,
including masonry and steel fixing.
He maintains that
his role was limited to providing skilled and semi-skilled workers and
executing the works under the company’s instructions.
He further claims
an engineer supervised the project and approved the works, raising fresh
questions about oversight, accountability and what went wrong before the
building came crashing down.
The two are among
more than 20 people who have so far recorded statements with police as
investigations into the tragedy intensify.
One of the three
developers has also given a statement, while the landowners are expected to
present themselves to police in the coming days.
Investigations
have also revealed that the landowners made two separate applications to
develop the property, paying Ksh.1.1 million to Nairobi County.
However, the
application remained pending on the national planning and development
management system after the project manager failed to address four issues
flagged by the county.
Meanwhile, after
eight days of sleepless nights, relentless digging and braving the scorching
sun, rescue teams on Friday morning recovered the dismembered remains of a
woman trapped beneath the rubble of the collapsed Eastleigh building.
The recovery was
made at around 6:30 a.m. in the basement, following an intensive overnight
operation to clear the debris and reach victims believed to be buried beneath
the wreckage.
National Disaster
Management Unit (NDMU Director Dr. Duncan Ochieng; said: “The body has been
taken to the mortuary for processing…the DNA will be carried out and we will be
able to identify who this fellow Kenya nwas.”
Nairobi North County
Commissioner Simon Osumba added: “Tutahakikisha wale familia wako hapa wamefikishwa
pale lakini zile process zetu zitafanyiwa hiyo mwili ndio sasa tuweze
kuhandover mwili kwa familia.”
Despite the latest
recovery, the number of people reported missing remains at 16.
This as another
family has come forward to report a missing relative to the Kenya Red Cross,
saying the individual was believed to be in the vicinity when the building
collapsed last Friday.

Join the Discussion
Share your perspective with the Citizen Digital community.
No comments yet
This discussion is waiting for your voice. Be the first to share your thoughts!